Use and Care Instructions for your new T2 Turgo Micro-hydroelectric Generator Models: MHG-T2 Asian Phoenix Resources Ltd., Canada PowerPal ™ T2 Turgo 1.
READ THIS FIRST This manual contains important informati on concerning your new PowerPal T2 Turgo micro-hydroelectric generator. It covers Model MHG-T2. You should read this manual carefully before installing PowerPal or allow a trained technician from your local PowerPal Service Center to install it for you.
POWERPAL COMPONENTS Inside your PowerPal box you will find: • 1 x generator-turbine assembly • 1 x penstock adaptor flange , internal diameter 110mm • 1 x rubber gasket • 4 x M10 foundation nuts and bolts • 1 x control panel including electronic load controller • 1 x ballast load • 1 x Guarantee Card • 1 x this instruction manual.
Turbine stand lt Forebay G F E D C B A A. Forebay, or water tank B. Atmospheric vent C. Penstock, or intake pipe D. Spear valve E. Turbine PowerPal ™ T2 Turgo 4.
SELECTING A SITE PowerPal is designed for use in a wide range of locations. There are two cr itical factors that influence power output – head and flow. Head is th e vertical distance between the turbine and the water source (for ebay), m easured in meters.
Measuring Flow The best way to measure the water flow is to tak e a piece of pipe the same diameter as the penstock, insert it in the stream or da m where the flow is expected to com e from, and measure the flow from there.
When installing the penstock, try to keep it as straight as pos sible and avoid sharp turns or angles. To do this, part of the hillslope may need exc avating while in other places the penstock may need supporting with poles etc. S teeper terrain has advan- tages over more gentle terrain as cost is reduc ed by the use of a shorter penstock.
SYSTEM INSTALLATION Mechanical Aspects After locating a suitable site and completing the civil works, your PowerPal is ready for installation. To do this: 1. Bolt the turbine to a turbin e stand or base which allo ws at least 300mm clearance between the turbine and the ground.
220VAC house suppl y Ballast load Electronic Load Controller - ELC Main network or house distribution boar d hydro turbine A B C To connect the electrical compone nts, please follow these steps: The electrics should be installed by persons competent in mains voltage wiring.
4. Connect the user load cables L1 and L2 between the control box and the house. 5. Connect the ballast load (C ) to the control box and user load cable. The ballast load is rated 10-15% (maximum ) higher than the rated power output of the generator e.
5. Operate like this for 15 minutes while observing any unusual noise, excessive temperature or other problems and if OK then switch on the power to the user. Up till now the ballast lo ad has been receiving all the power and should be hot, but once switching on the user load the powe r to the balla st load will fall.
Changing the Bearings and Seal Apart from greasing the bearing, there are on ly two tasks that m ust be completed at regular intervals. These are the changing of the lower generator bearing & turbine bearing and the lower bearing seal every two years.
E F C D A B TROUBLESHOOTING If any problems are encountered, check this section before contacting your Service Center. 1. Head and flow conditions appear to be OK, but PowerPal will not work. It is likely that the system has been installed in correctly.
2. PowerPal has provided el ectricity for a while and suddenly the electricity stops. If this instruction manual is not followed and power consumption is too high, or if there is a short circuit in an appliance th e circuit breake r in the electronic load controller will trip.
a) Start the generator and ad just the spear valve to obtai n 220-240 volts, 0 amps at the panel. [Do not turn the circuit breaker on]. b) Adjust the potentiometer on the circuit board very slowly to the left. When you detect a small decrease in voltage, stop.
APPENDIX A – FOREBAY DESI GN The instructions given on page 7 of this manual to design the forebay are adequate for most cases. The most important aspects of forebay design are: 1) To allow a continual flow of water to the penstock so tha t the turbine keeps functioning.
POWERPAL T2 TURGO MODELS T-2 Model (1.5kW) (single nozzle) Output (watts) H (head, in metres) 14 15 16 17 18 19 20 Q (flowrate, in l/sec) 18.5 17. 3 16.2 15.2 14.4 13.6 12.9 1250 18.5 17.3 16.3 15.4 14.6 13.9 1361 18.5 17.4 16.5 15.6 14.8 1452 18.5 17.
Een belangrijk punt na aankoop van elk apparaat Asian Resources Int'l Limited MHG-T2 (of zelfs voordat je het koopt) is om de handleiding te lezen. Dit moeten wij doen vanwege een paar simpele redenen:
Als u nog geen Asian Resources Int'l Limited MHG-T2 heb gekocht dan nu is een goed moment om kennis te maken met de basisgegevens van het product. Eerst kijk dan naar de eerste pagina\'s van de handleiding, die je hierboven vindt. Je moet daar de belangrijkste technische gegevens Asian Resources Int'l Limited MHG-T2 vinden. Op dit manier kan je controleren of het apparaat aan jouw behoeften voldoet. Op de volgende pagina's van de handleiding Asian Resources Int'l Limited MHG-T2 leer je over alle kenmerken van het product en krijg je informatie over de werking. De informatie die je over Asian Resources Int'l Limited MHG-T2 krijgt, zal je zeker helpen om een besluit over de aankoop te nemen.
In een situatie waarin je al een beziter van Asian Resources Int'l Limited MHG-T2 bent, maar toch heb je de instructies niet gelezen, moet je het doen voor de hierboven beschreven redenen. Je zult dan weten of je goed de alle beschikbare functies heb gebruikt, en of je fouten heb gemaakt die het leven van de Asian Resources Int'l Limited MHG-T2 kunnen verkorten.
Maar de belangrijkste taak van de handleiding is om de gebruiker bij het oplossen van problemen te helpen met Asian Resources Int'l Limited MHG-T2 . Bijna altijd, zal je daar het vinden Troubleshooting met de meest voorkomende storingen en defecten #MANUAl# samen met de instructies over hun opplosinge. Zelfs als je zelf niet kan om het probleem op te lossen, zal de instructie je de weg wijzen naar verdere andere procedure, bijv. door contact met de klantenservice of het dichtstbijzijnde servicecentrum.